An aircraft of the UK's RAF lands on the new runway at RAF Brize Norton

Air Force

RAF Brize Norton reopens with a new 3 km runway, replaced in 16 weeks

The UK Ministry of Defence says aircraft are back at RAF Brize Norton after the station's 3 km runway was fully replaced in 16 weeks, the first major milestone of a £180 million airfield programme.

Photo: MOD Crown Copyright

Aircraft have returned to RAF Brize Norton after the station’s 3 km runway was replaced in full in 16 weeks, the UK Defence Infrastructure Organisation (DIO) announced on 18 November. The first aircraft touched down on the new surface on Friday, 13 November.

Brize Norton is the Royal Air Force’s main air transport hub in Oxfordshire. According to the DIO, the runway work is one part of a £180 million programme to overhaul the station’s critical airfield infrastructure.

What was built

The DIO handed the finished runway to Air Commodore Phil Reid, the RAF’s Head of Air Infrastructure. VolkerFitzpatrick carried out the works, with AECOM providing technical services.

Advertisement

The new runway uses Pavement Quality Concrete and Grooved Marshall Asphalt. The DIO says these materials were chosen to cope better with higher temperatures and the effects of climate change, and that the concrete is expected to more than double the runway’s service life compared with the materials used before.

Operations during the closure

Aircraft were dispersed to several alternative locations during the 16 weeks of construction, which allowed operations to continue while the runway was out of use, the DIO said.

Mike Green, the DIO’s Chief Executive, called the result “a tremendous team effort” and said the work had been delivered at pace while keeping the RAF’s operational needs in focus. Bob Noyes, the DIO’s principal project manager, said it was “fantastic to see aircraft returning home” and described the station’s role in military operations around the world.

What happens next

The runway is only one element of the programme. Work continues on taxiway refurbishment, airfield lighting upgrades, and drainage and supporting infrastructure, and Air Commodore Reid said the effort will continue until overall project completion late in 2027. The programme is funded through the Defence Investment Plan.

For the RAF, the aim stated by the DIO is to keep the base fully operational for decades, strengthening the airfield’s long-term strategic and operational capability, safety and resilience.

Source: UK government (DIO) announcement.